Electrical installation
Control terminals
4
98
EDKCSEE040 DE/EN/FR 4.0
Switch-on sequence for the auxiliary relay
Stop!
Overload of the charging connection in the power supply module
Thecontrollerenablefortheaxesmayonlytakeplacewhenthe
charging process of the DC bus is completed and the power supply
module is ready for operation.
Possible consequences:
ƒ Destruction of the power supply module
Protective measures:
ƒ Use of switching the central controller enable for the axes via the
inputs and outputs DI2 and DO1 of the power supply module
(see the following descriptions).
The switch-on sequence of the auxiliary relay (see Fig. 4-8) is as follows:
1. The digital input X6/DI1 (power supply enable) of the power supply
module is switched to HIGH by the higher-level control or by the operator.
– The DC bus is charged.
2. The ready for operation output of the axis module (DO1) now switches
the X6/DI2 digital input (central controller enable) of the power supply
module via the relay .
– In the default Lenze setting of the ECS axis modules, DO1 is set to
”ready”. ”Ready” is only present if a specified DC-bus voltage has been
reached.
3. The central controller enable for the axis module takes place via the
X6/DO1 output of the power supply m odule. The central controller enable
DO1 o nly switches if the charging process of the DC bus is completed AND
the X6/DI2 input is set.